How long does a website redesign take? The 6-stage redesign process: 6–10 weeks for a brochure site, 12–20 weeks for e-commerce or membership sites, with content migration and 301 redirects causing most delays, so export your old URL list first

2026.11.16 · 88 views
How long does a website redesign take? The 6-stage redesign process: 6–10 weeks for a brochure site, 12–20 weeks for e-commerce or membership sites, with content migration and 301 redirects causing most delays, so export your old URL list first
“

A redesign slips more easily than a brand-new build because old content, old URLs and old member data all have to be handled. We cover a timeline table by site type, the six stages of a redesign with deliverables and what you should confirm at each, five common causes of delay, and a checklist to gauge your project's complexity. ”

Share:

Direct answer: How long a redesign takes depends on how much content and data must move: about 6–10 weeks for a brochure site and 12–20 weeks for e-commerce or membership sites. The redesign process has six stages; content migration and 301 redirects cause most delays, so exporting your old URL list first saves 2–4 weeks.

The pain: five months of redesign, then inquiries halved after launch

Owners fear not knowing where the project stands or whether launch will break things more than the time itself. An industrial parts company planned a two-month website redesign; copy arrived late and 180 product pages had to be re-entered, so it launched in month five. In the first week, every old product URL in Google returned 404, monthly inquiries fell from 60 to 28, and six more weeks of redirect fixes were needed before they recovered. A planned redesign process would have avoided all of it.

How long does a redesign take? Timeline by site type

A redesign takes about 2–4 weeks longer than a new build, and the extra time is migration and redirects.

Site typeRedesign timeWhere extra time goesTypical budget
Brochure site (10–30 pages)6–10 weeksRewriting copy, sorting old imagesNT$30K–150K
Product catalog site (100+ pages)8–14 weeksMoving product data, standardizing spec tablesNT$100K–300K
E-commerce site12–18 weeksMoving products, members and orders; retesting paymentsNT$200K–600K
Membership or booking site12–20 weeksMigrating accounts and points, handling passwordsNT$250K–800K

The six stages: what happens, what is delivered, what you confirm

Each stage ends with a deliverable you sign off before moving on, which keeps progress under control.

  • 1. Audit (1–2 weeks): Export every old URL, the top 20 pages in Google Analytics and the current feature list. Deliverable: URL and content inventory. You confirm: which pages bring inquiries or orders; none can be dropped.
  • 2. Requirements and structure (1–2 weeks): Decide whether each page is kept, merged or removed and draw the new menu. Deliverable: sitemap and feature spec. You confirm: main products are reachable within three clicks.
  • 3. Design (2–4 weeks): Homepage plus 3–5 inner page templates. Deliverable: designs. You confirm: the mobile view, with feedback collected in one round.
  • 4. Build and content migration (3–10 weeks): Build the site and move articles, products and member data. Deliverable: a staging site. You confirm: who moves content and by when.
  • 5. Testing and redirects (1–2 weeks): Test forms, payments and login, and build the old-to-new 301 redirect map. Deliverable: test report and redirect map. You confirm: click through the top 20 pages one by one.
  • 6. Launch and monitoring (4 weeks after launch): Switch the domain, submit the sitemap and monitor Search Console errors following Google's guide to site moves with URL changes. Deliverable: 30-day post-launch report. You confirm: inquiries and orders did not drop.

Common causes of delay and how to avoid them

About 80% of redesign delays come from the client's content and decisions, not from coding.

  • Late copy and photos: Set content deadlines at kickoff; one week late means one week later launch.
  • Underestimated migration: With 100+ products, check whether Excel batch import works; manual entry takes 5–10 minutes per item.
  • Endless design changes: Limit each stage to two revision rounds, with feedback gathered by one contact.
  • No 301 redirects: Export the old URL list in stage 1 and map it line by line in stage 5.
  • Missing domain and hosting access: Confirm the domain registrant and DNS access before starting; this often stalls projects 1–2 weeks.

Fix speed too: before launch, measure LCP with PageSpeed Insights and aim for under 2.5 seconds on mobile, or the redesign only changed the look.

Decision checklist: how complex is your redesign?

Five or more checks means plan for 12+ weeks and treat content migration as its own work item.

  • ☐ More than 50 pages
  • ☐ More than 100 products or articles
  • ☐ Member accounts to migrate
  • ☐ Online payments or order data
  • ☐ URL structure will change
  • ☐ Organic search drives 30%+ of inquiries or orders
  • ☐ Integration with ERP, CRM or logistics
  • ☐ Bilingual or multilingual
  • ☐ Copy and photos must be redone
  • ☐ The old vendor cannot be reached

Frequently Asked Questions

How long does a website redesign take?

About 6–10 weeks for a brochure site and 12–20 weeks for e-commerce or membership sites; more content and data mean longer.

Will a redesign hurt SEO rankings?

Changed URLs can cause short-term swings; with proper 301 redirects most sites recover within 2–8 weeks.

Can we redesign in phases?

Yes, start with the homepage and high-traffic pages, but switch checkout and membership at once to avoid two data sets.

What should we prepare before a redesign?

An old URL list, top 20 pages by traffic, a list of features to keep, and access to domain and hosting accounts.

Next step: get a redesign timeline first

ScriptWalker (a Taiwan-based Laravel/Flutter custom development studio) handles website redesigns from NT$15,000 for websites and NT$80,000 for systems, and every project includes a redesign timeline, an old URL inventory and a 301 redirect map. Send us your URL for a free estimate of how long your redesign will take and what needs migrating: